Task #2675

Automation of product integration tests - prerequisities

Added by Ondrej Husník 2 months ago. Updated about 2 months ago.

Status:
Closed
Priority:
Normal
Category:
Test
Target version:
Start date:
02/08/2021
Due date:
% Done:

100%

Estimated time:
Milestones:

Description

The goal is to automate manual tests of common IdM features according to the prepared test scenarios.


Related issues

Related to CzechIdM - Task #2665: Verification of product test scenarios.Closed01/26/2021

Related to CzechIdM - Task #2636: Investigate Squash test systemClosed01/08/2021

Related to CzechIdM - Task #2693: Initialization of mock target system for product integration testsNew02/26/2021

History

#1 Updated by Ondrej Husník 2 months ago

  • Related to Task #2665: Verification of product test scenarios. added

#2 Updated by Ondrej Husník 2 months ago

  • Related to Task #2636: Investigate Squash test system added

#3 Updated by Ondrej Husník 2 months ago

  • % Done changed from 0 to 30
At this moment there is implemented majority of initialization phase.
  • both hrContract and hrIdentity source systems are implemented
  • LRTs following contract sync are triggered
  • synchronized identity has correctly generated username and email
  • all automatic and business roles and their organization in catalogues are created
  • automatic roles based on organization structure are assigned
  • automatic roles based on contract attribute are assigned

There remain to configure destination systems as a part of the initialization phase.
Unfortunately already implemented Ldap system is placed in the RPT module which makes it inaccessible from Acc module.

#4 Updated by Ondrej Husník about 2 months ago

  • Related to Task #2693: Initialization of mock target system for product integration tests added

#5 Updated by Ondrej Husník about 2 months ago

  • Subject changed from Automation of product integration tests to Automation of product integration tests - prerequisities
  • Status changed from In Progress to Resolved
  • % Done changed from 30 to 100

The phase of test data preparation was done and following configuration of target systems will be performed in next ticket.

#6 Updated by Radek Tomiška about 2 months ago

  • Status changed from Resolved to Closed